To agree the delivery of the scheme of building works required to complete the 2FE expansion of Invicta Primary School on Benbow Street, Deptford. This represents the last phase of the series of prior refurbishment works carried out at the site; and will ensure the provision of additional classrooms, administration offices, outdoor playground and other essential facilities required by a fully-fledged 2FE school from September 2019.

 

To agree the total project budget of £1,946,955.98 (inclusive of design, project & cost management fee, construction and project risk management) to carry out required works.

 

To agree In accordance with CSO 23.2 agree to award the contract to Hasbridge Construction Ltd for the refurbishment and remodelling works of Invicta Primary School-  for the sum of £1,400,414.98

 

To delegate to the Director of Regeneration, Enterprise and Skills in consultation with the Director of Children’s Services the authority to vary the scheme in accordance with identified priorities.

 

To agree to treat the information presented in the appendix as exempt under the provisions of the Local Government Act 1972, Schedule 12A, and that this information is not subsequently released to the press or public.

 

 

 

 

Publication date: 20/05/2019

Date of decision: 20/05/2019

Effective from: 25/05/2019