Scheme & Estimate - for the provision to remodel Plumstead Manor School, Old Mill Road, London SE18 1QF, allowing transformation from single gender to co-ed School

Decision Maker: Deputy Leader of the Council (Regeneration & Sustainability)

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

1.          To agree delivery of the scheme of building works required to convert Plumstead Manor Secondary School from a single-sex girls school to co-educational facility.

2.          To agree the total budget of £618,155.72 to carry out required works including improved DDA lift access requirements.

3.          To note that a building contract for the scheme has not yet been tendered and the detailed design work is to be finalised. Whilst there is a risk allowance built into the budget to cater for this, due to the stage the project is at it is difficult to accurately predict the project costs.

4.          To delegate to the Director of Regeneration, Enterprise and Skills in consultation with the Director of Children’s Services the authority to vary the scheme in accordance with identified priorities.

Decision:

1.          Agreed delivery of the scheme of building works required to convert Plumstead Manor Secondary School from a single-sex girls school to co-educational facility.

2.          Agreed the total budget of £618,155.72 to carry out required works including improved DDA lift access requirements.

3.          Noted that a building contract for the scheme has not yet been tendered and the detailed design work is to be finalised. Whilst there is a risk allowance built into the budget to cater for this, due to the stage the project is at it is difficult to accurately predict the project costs.

4.          Agreed to delegate to the Director of Regeneration, Enterprise and Skills in consultation with the Director of Children’s Services the authority to vary the scheme in accordance with identified priorities.

Publication date: 13/04/2018

Date of decision: 06/04/2018

Effective from: 21/04/2018